Sr.ParticularSequence of Activity
1Quote to customer of his Inquiry as per his requirementQuotation
2Drawing Sample and order with Schedule are Received from CustomerOrder / Planning
3Job card release/Whole Designing And detail designing and preparing parts drawingDesign / Release
4Order to vendor for raw material requirement or order to customer for arrangeRaw Material Order
5Received raw Material(casting or bar or block) from customer / outside vender sourceRaw Material Inward
6Checked raw goods and if require prepare pre-machining drawingInspection
7Send it to vendor or in-house conventional shop for pre-machining/part making with drawingPre-machining (Conventional Shop)
8Received it to VMC/CNC shop and checked pre-machining dimensionCNC Shop / Inspection
9Prepare programme and inspection report with set up sheet andProgramming/Setting
10Inspect during machining after each programmeIn process Inspection
11After completed VMC/CNC process send it for final inspectionInspection
12Send it to conventional shop for Assembly(all part from VMC and conventional and readymade)Assembly
13After Assembly completed polished goodsPolishing
14After polishing and Assembly inspect all thoroughlyInspection
15If require, trial all AssemblyTrial
16Packing in boxes for DispatchPacking
17Dispatch with required DocumentsDispatch
Flow Process

Machinery Components

Sr.ParticularSequence of Activity
1Quote to customer of his Inquiry as per his RequirementQuotation
2Drawing Sample and order with Schedule are Received from CustomerOrder / Planning
3Received raw Material(casting or bar or block) from customer / outside vender sourceRaw Material Inward
4Prepare Job card & Checked raw goods and if require prepare pre-machining drawingSchedule / Designing
5Send it to vendor or in-house conventional shop for pre-machining with drawingPre-machining (Conventional Shop)
6Received it to CNC shop and checked pre-machining dimensionReady for CNC shop/Inspection
7Prepare programme and inspection report for production as per job cardProgramming/Setting
8First piece checked thoroughly after trial and before start productionTrial/Inspection
9After completed CNC process send it for final inspectionInspection
10Send it to VMC shop(Vendor) if its requireVMC/Milling process
11After VMC completed deburred(polished) goods send it for hole andHole/Tapping
12Hole And Tapping Done By Using Jigs And Fixture As Per Require QualityHole/Tapping
13After Finished All Operation, Polished And Cleaning And Deburred All ComponentsPolishing/cleaning
14Final Inspection Report Fill Up And CheckedFinal Inspection
15Packing in Boxes for DispatchPacking
16Dispatch with required DocumentsDispatch